Steady progress through the floods at Neen Sollars

Installation work continues at a good pace, despite inevitable delays caused by the near-constant floods for the last few months, now alternating with periods of low temperatures which mean concrete work cannot be carried out. The cofferdam upstream and downstream … Continue reading

Installation work continues at a good pace, despite inevitable delays caused by the near-constant floods for the last few months, now alternating with periods of low temperatures which mean concrete work cannot be carried out.

The cofferdam upstream and downstream is holding well despite the River Rea flowing fast over the last two months, the tailrace is now largely completed with gabion baskets, and work has started in the original wheel pit strengthening walls and making the concrete structure for housing turbine and generator.  NSCH has already contracted a local electrician to prepare for the generator installation and dovetail the necessary work connecting to grid. We reckon to be generating around Easter at this rate. wheelpit wheelpit2