Welcome

Neen Sollars Community Hydro owns and runs a 12.5kW hydroelectric installation at Tetstill Mill, Neen Sollars on the River Rea. The project is funded by a co-operative share issue and owned by local people. The turbine will provide green electricity to the local electrical grid, corresponding to around 20% of the domestic power use in Neen Sollars.

  • practical generation of green electricity
  • local involvement in owning and running a renewable generation system
  • awareness raising and education in the local area
  • a modest annual income for a local charity
  • entirely conceived and executed by local people
  • working alongside wider attempts to improve the ecological status of the Rea

The turbine has had serious operational issues due to the installer going bust but is being brought back into full production by a volunteer team of members and supporters.

Posted in Info | Leave a comment

Successful tests

Turbine connected to grid and exporting at 5.2 kW in test mode

The volunteer team working on the turbine have had a notable breakthrough – power has been generated at the site.

Members of the team have been working hard to repair and test the installation over recent months, most recently replacing some ‘stop logs’  – a kind of downstream dam which keeps the outflow tube of the turbine submerged. Nobody had realised quite how essential this item was – when the previous logs had been washed away in a flood, it was thought that this would only reduce efficiency of the turbine. It turns out that the plant simply does not function without this dam. Now the replacement is in situ, the team has managed to generate power for the first time in several months.

Trials of continuous running await higher river levels – England has seen six successive months of below-average rainfall – but with significant rain forecast this week we are hopeful that we will soon be in a position to make a start.

There remain significant mid-term challenges on site – lubrication system, monitoring system and debris screen all need work. But this is a genuine breakthrough for the team and reflects a considerable amount of work done by members and supporters on site.

 

 

Posted in Info | Comments Off on Successful tests

Hydro plant revival project underway

The hydro plant is currently non-operational and has worked sporadically since it was installed in July 2014. Following initial teething issues Ampair, the company that designed and installed the turbine, went bankrupt in February 2015 leaving the plant not completely functional. NSCH has attempted to work to get the turbine working again with sporadic support from previous Ampair employees and others but it has become clear that a more comprehensive approach is needed.

NSCH believes that the turbine and civil works are fundamentally sound and that the turbine can be brought back into operation. A team has been brought together of members of the Society and supporters from outside the Society. This team aims to get the turbine reliably operating at the relatively low level of 5kW by the winter season beginning October 2018.

This plan is well advanced and technical experts Derwent Hydro are due on site at the end of March 2018 to carry out works aimed at getting the turbine working reliably. A work party of members and supporters is cleaning the site in preparation on 23 March.

Funding has been obtained from 3 sources. Firstly, several members have kindly offered interest-free loans. Second, Sharenergy Co-operative have offered free annual administration for the project to date and deferral of funds owed from the inception of the project (and have also made an interest-free loan). Third, we have had a very generous grant from Leominster Community Solar which has been invaluable in getting us on the right track.

Posted in Info | Comments Off on Hydro plant revival project underway

Sad news at Tetstill

It is with great sadness that we learn of the death of John Bettinson, owner of and resident of Tetstill Mill. He was the most wonderful supporter or our project – firstly agreeing to let us build a community hydro plant at his home, and then through the intervening years providing so much in the way of flexibility, constructive criticism and good humour. Along with all who knew him will will miss him greatly.

John Bettinson addressing an early NSCH AGM

John Bettinson addressing an early NSCH AGM

 

 

Posted in Info | Comments Off on Sad news at Tetstill

Awards and technical progress

MidcountiesPrinciple 6 of the International Co-op Principles states that co-ops help each other out – we were the lucky recipient of co-ops in action when Midcounties Co-operative gave us a very welcome £2,000 grant to help with the additional costs we’ve been incurring getting the turbine properly running. We’re very glad to say that the faulty actuator on the turbine has now been replaced and the turbine is now humming away, albeit at a reduced power level of 2kW until all the grid testing is complete.

Posted in Info | Comments Off on Awards and technical progress

January update

A little while since our last update and a lot has happened. We have had the turbine up and running in test mode and it has produced some energy. The final step to consistent generation is unfortunately taking a lot longer than we hoped. Firstly we encountered some serious snags in the last stages of the civil work – see previous updates for the huge and rock-hard stump we found right in the place where the screen was supposed to go! The delay there had a knock-on effect on installation of the turbine assembly. Once the turbine was fully in place we encountered some problems with the grid voltages meaning each time we switched it on, it tripped out! Finally the ramifications of the delays and difficulties have caused cashflow problems for the co-op. This has all been especially frustrating because river flows have been good for the last few months, but we’ve been unable to benefit from this to make some much-needed income for the co-op.
We’re pleased to say that after a lot of work and negotiation with suppliers we finally feel like we have a working plan to get the turbine up and running very soon. Firstly the co-op will be making a bond issue of around £20,000 to members to raise the additional working capital we need to cover the over-run. At the same time, we are working intensively with our civils contractors and the turbine suppliers to get the turbine spinning reliably. One silver lining in the situation is that we are benefitting from some of the optimisation which has been carried out on a turbine of the same type installed just before ours.
Posted in Info | Comments Off on January update

Stump out and on we go

thestumpThe rain has come right on time as we enter what is hopefully the final week of installation. The famous stump that we found at the base of the weir has been removed finally and last Friday the slab which will sit below the inlet screen was cast. The screen is set to go in place towards the end of the week – then we can remove the temporary dam and the installation will be physically complete. Our turbine ought to see its first flows for commissioning purposes sometime next week – if that goes well we hope to harvest a little of this rain perhaps even before October is out.

Posted in Info | Comments Off on Stump out and on we go

Generator in place

The generator installation was completed on Friday. The system is essentially ready to go once we have the inlet screen in place, which will probably take us into early next week. The photos also show the new eel pass in action. As you can see, flows are still low, so we will have to wait a little while for our first energy generation.

Posted in Info | Comments Off on Generator in place

Turbine arrives on site

The turbine is being installed as we speak. Bill comments “The quality of workmanship is impressive. We will have a powerful piece of equipment here – all we need is the river to help us along. With current very low flow conditions we’ll probably only have a ‘window’ for commissioning and then have to shutdown”. Let the rain hold off for a few days while we install and then Autumn can get going properly!

Posted in Info | Comments Off on Turbine arrives on site

Civil works complete

They say 90% of a hydro project is in the civil engineering. These photos just in really show how much work has gone in. The first picture is from the period of floods when work on this area was just starting:

We’re still awaiting the turbine itself but assured that it is on its way very soon!

Posted in Info | Comments Off on Civil works complete

First parts of turbine in place

The turbine house is finished and the capture ring is in place – this is the interface between the turbine and its housing. The draft tube will be next – this is the outflow of the turbine – we have agreed a slight shape modification which will increase efficiency. After that the propellor itself and the generator will go in – this should take a couple more weeks and we will be ready to make power from the rain now falling!

Posted in Info | Comments Off on First parts of turbine in place