Monthly Archives: December 2011

We did it!

We have met the target of £150,725 for the share issue and we’re actually oversubscribed! Thank you to everyone who has supported the project, we are delighted with this response, it’s been overwhelmingly positive. The share issue will close as … Continue reading

Posted in Uncategorized | Comments Off on We did it!

Great Event – and almost there on share offer!

Thank you to all of you who made it out last night, for what was a fantastic evening, to celebrate the installation and registration of the array before the proposed deadline. Over 60 people attended, which given that at the … Continue reading

Posted in Uncategorized | Comments Off on Great Event – and almost there on share offer!

Join the celebration – Tuesday 6-8pm

We will be holding a celebratory event at the Bridge Street Sports Centre in Leominster on Tuesday 13th December between 6-8pm, to mark the successful completion of the installation and its registration for FITs on Friday before the government’s proposed … Continue reading

Posted in Uncategorized | Comments Off on Join the celebration – Tuesday 6-8pm

The Finished Article

And we just heard from Good Energy that our application for FiTS is accepted. See you Tuesday  – members and potential members all welcome!

Posted in Uncategorized | Comments Off on The Finished Article

Up and running

We generated our first few kWhs a few minutes ago and have our MCS certificate – Eithne is now busy getting the paperwork done to make sure we are correctly registered for FiTS in time! If you were waiting to … Continue reading

Posted in Uncategorized | Comments Off on Up and running

Thursday update

Its a battle against the weather right now – we love a bit of wind but could it wait until Monday please! Some pics from yesterday

Posted in Uncategorized | Comments Off on Thursday update

Midweek update

Latest from the installers: We have over 100 panels on at Halo, another 58 planned today, scaffolding alteration booked in for tomorrow morning, remaining panels on tomorrow. Tomorrow (Thursday) we will also have the electrical witness testing going on for … Continue reading

Posted in Uncategorized | Comments Off on Midweek update

Half way point!

On schedule, the first half of the array is now installed and the scaffolding is in the process of being moved, to enable the second half to start going on tomorrow.  More photos to follow soon.

Posted in Uncategorized | Comments Off on Half way point!

Panel installation starts

Panels and mounting gear are on site and installers are up on the roof, racing against time to ensure the installation is completed in good time for registration before 12th December.  The photo here shows progress so far, with panels … Continue reading

Posted in Uncategorized | Comments Off on Panel installation starts